----------------------------------------------- Blogger Template Style Name: Simple Designer: Blogger URL: www.blogger.com ----------------------------------------------- */ Print Friendly and PDF /* Variable definitions ==================== body { -webkit-user-select: none !important; -moz-user-select: -moz-none !important; -ms-user-select: none !important; user-select: none !important; }

More than 10000 MCQs

Read more than 10000 MCQs, Notes, Quiz, Railway Codes, Railway Manual, Labour Laws Rules & Act, Railway GK, Rly.Accounts, Rajbhasha & more different topics of Indian Railway Departmental Examination (Non-Technical) to enhance your knowledge

Tuesday 2 May 2023

IRPSM- Indian Railways Projects Sanctions & Management, Plan Heads Co-ordinators

 

IRPSM

 

Ø Full form is “Indian Railways Projects Sanctions Management.

 

Ø That means it has two broad divisions.  

1) Sanctioning of new projects i.e., Works Programme and

2) Management/Monitoring of such sanctioned Projects. Web based application i.e., usable only with an internet connection and uses HTTP (Hyper-Text Transfer Protocol) as its primary communication protocol.

 

Ø Developed by CRIS, New Delhi ( All the system administration functions, viz Operating System, Database, Application Server besides day to day operation – responsibility of CRIS)

 

OBJECTS OF IRPSM

 

Ø Online creation and forwarding of “NEW WORKS” proposals from the Zonal Railways and Production Units to the Railway Board duly replacing the existing manual system.

 

Ø Modifications to the “Works in Progress”

 

Ø Printing of Works programme, Pink Book and other sanction books after sanction by Railway Board.

 

Ø Monthly updating of status of various works by executing agencies like Sr.DEN, Sr.DOM etc.

 

Ø Monitoring of all Works/Projects.

 

TYPES OF USERS

 

LEVEL/USER

PLAN HEAD CO.ORDINATOR

WORKS PROGRAMME        CO.ORDINATOR

SANCTIONING AUTHORITY

DIVISION

Branch officers like Sr.DOM, Sr.DME etc

Sr.DEN/Co

DRM

ZONAL RAILWAY

PHODs

CPDE – Chief Planning & Design Engineer

GM

RAILWAY BOARD

-

EDCE(G) – Executive Director Civil Engineering (General)

Railway Board & Minister for Railways

 

 

Plan Heads and Plan Head Co-ordinators

 

PH No

PH Name

Plan Head Coordinator

Divisional

Zonal Rly/PU

11

New Lines

Sr.DOM

COM

14

Gauge Conversion

15

Doubling

16

Traffic Facilities

35

Electrification Projects

81

Metropolitan transport projects

 

 

PH No

PH Name

Plan Head Coordinator

Divisional

Zonal Rly/PU

29

Level Crossing Gates

Sr.DEN/Co

CTE

30

ROB/RUB

CBE

31

Track Renewals

CTE

32

Bridge Works

CBE

51

Staff Quarters Welfare

PCE

52

Staff Amenities

PCE

64

Other Specified works

PCE

 

 

PH No

PH Name

Divisional

Zonal Rly/PU

17

Computerisation

Sr.EDP

CCM

33

S & T

Sr.DSTE

CSTE

36

Other Electrical Works

Sr.DEE

CEE

42

Workshops

Sr.DME

CWE

53

Customer Amenities w.e.f. 16.8.2021

Sr.DCM

CCM

 

 

IRPSM @ DIVISIONAL LEVEL

 

Ø Creation of “New Works” proposal with justification & Abstract Cost.

 

Ø Forward to Finance (Sr.DFM) for vetting.

 

Ø Sanction of Proposal  - by DRM (if within DRM powers)

 

Ø Forwarding of proposals to Zonal Railway ( If beyond DRM’s powers)

 

Ø Adding all the Works sanctioned under DRMs powers – to the list of “IN PROGRESS” works in IRPSM.

 

Ø Assigned unique Project ID as explained below.

 

Ø Reporting of status every month for each work by respective Exexutive Agency.

 

Ø Generation & Printing (if desired only) of Works Programme reports.

 

IRPSM @ ZONAL RAILWAY LEVEL

 

Ø Examination and processing of “New Works” proposals as received from Divisions will be forwarded by CPDE – Chief Planning & Designs Engineer the respective Zonal Plan Head Co ordinators.

 

Ø Creation of “New Works” proposals.

 

Ø Forward to Finance (FA&CAO) for vetting.

 

Ø The vetted proposals forwarded by Plan Head Co.ordinators will be checked and then forwarded to GM through PCE for Sanction.

 

Ø Sanction of Proposal  - by GM (if within GM powers)

 

Ø Forwarding of proposals to Railway Board ( If beyond GM powers)

 

Ø Adding all the Works sanctioned under GM powers – to the list of “IN PROGRESS” works in IRPSM.

 

Ø Assigned unique Project ID as explained below.

 

Ø Defining Funds availability & Sanction limits for Zonal Railway HQ & Divisions.

 

Ø Reporting of status every month for each work by respective Executive Agency.

 

Ø Generation & Printing (if desired only) of Works Programme reports.

 

IRPSM @ Railway Board Level

 

Ø Forwarding of proposals received from Zonal Railways by EDCE(G) to Nodal Directorates for respective Plan Heads.

 

Ø On line shortlisting, Recommedning& Forwarding to EDCE(G)

 

Ø Above 5 Crores each -  Proposals forwarded by Nodal Directorates to EDF(X) – I & II for Finance Concurrence.

 

Ø Below 5 Crores each – Online shortlisting, recommending & forwarding to EDCE(G) by Nodal Directorates through concerned AMs (Additional Members) for Plan Heads.

 

Ø Compilation of all shortlisted proposals (Below 5 Crores each) by EDCE(G) for meeting of AM’s committee

 

Ø At any time, ON LINE YELLOW SLIP can be attached on-line and file can be moved out of the normal path for consultation.  All yellow slip communications will be kept off the general record provision for the off-the-record consultation on Proposals.

 

Ø Such shortlisted & recommended proposals for each Plan Head with On-line consent and remarks of Finance will be processed by Nodal Directorates through EDCE(G) on the file for approval of Board & Honorable Minister for Railways.

 

Ø Assigned unique Project ID as explained below.

 

UNIQUE PROJECT ID  - 14 DIGIT

1

2

3

4

5

6

7

8

9

10

11

12

13

14

Zonal Rly

Division

Plan Head

Year of sanction

Authority sanctioned (like GM,DRM etc)

Executing Agency (Like Sr.DEN or Sr.DOM)

Serial Number

 

 

UNIQUE PROJECT ID  - 14 DIGIT  -

an example of Passenger Amenities Work (Plan Head 53) Sanctioned by GM in Mumbai Division of Central Railway

 

0

1

0

2

5

3

1

6

3

0

0

0

0

7

Central Railway

Mumbai Division

Plan Head

2016-17

GM

Not identified

Serial Number

 

Hence Project ID for the above work is “01025316300007”

 

ADVANTAGES OF IRPSM

Ø A paperless office.  All files will move online without involvement of physical files.

Ø Completely reduce transit time of file from one office to another.  Proposals reach Boards office within no time.

Ø All requisite justification, plans, drawings, sanctions and permissions will be attached to the proposals.

Ø Online monitoring the work in progress of all the works.

-:o:-