CREW LINKS, LOCO LINKS AND POWER PLAN
PROCEDURE FOR CALCULATING CREW REQUIREMENT OF A DIVISION
1. Running staff review should be carried out after every six months i.e. on 1st Jan. and 1st July by STA (Senior technical assistant) of the division.
. Before preparing review, loco pilot's links of all the sheds should be got prepared and vetted by personnel branch.
3 Statement of avg. hours on road and no. of goods . Trains ran during last six months for each section should be ready duly approved by Sr. DOM/DOM.
4. A list of shunting' points and DMTs running to be prepared and signed by Sr. DOM/DOM.
5. Mail/Express/Passenger Loco pilots requirement to be worked on the basis of loco pilots/crew links.
6. For goods crews_ the requirement should be worked out as per power plan signed by Sr DME(P) and Sr. DOM. 7.67 Crews are to be demanded for one freight POL. Separate crews to be demanded for the activities which cannot been covered in power plan e.g., Light engine and Empty coaching rakes running etc.
7. 30% leave reserve and 10 % trainee reserve should be demanded for this additional requirement.
8. Shunters should be demanded @ 1 against 8 hrs. point. Also rest giver @ 1 for 6 shunters to be demanded. Leave reserve and trainee post to be demanded separately.
9. Requirement of DSL assistants should be same as that of loco pilots (Excluding motormen where no assistant loco pilot is required).
10. Running staff review duly signed by Sr. DME/Sr. DEE should be put up to Sr. DAO for vetting.
11. After accounts vetting sanction of DRM be taken and Sr. DPO will issue circulars of revised sanction. + Running supervisors review should also be made with staff review @ 1 loco Inspector against 25 loco pilots or 50 shunters. No rest giver allowed. Leave reserve 12.5%.
POINTS TO BE KEPT IN VIEW WHILE PREPARING LOCO PILOT'S LINKS
1. Loco pilot/Crew links are prepared by CPRC/CTLC and got verified from Personnel Branch. Objective of crew links is to ensure optimum utilization of crews.
2. Train timings to be checked from the latest timetable.
3. Links to be prepared before promulgation of new time table.
4. Max. duty hours in anyone trip should not exceed 10 hours.
5. Avg. duty hours in a fortnight should not exceed 104 hours.
6. Min. no. of rests in a month should be included in the link.
7. Efforts should be made to include all the sections in the link to avoid giving learning road again and again.
8. Min. out of station rest in case less than 8 hrs. duty in the previous trip should be 6 hrs from sign off to sign on. In case duty is 8 hrs or more than 8 hrs, then 8 hrs. rest to be given. In case of short trips of less than or equal to 5 hours then duty performed plus 1 hrs. will be sufficient. 132
9. Min. home station rest should be (a) If duty performed in the last trip is less than 8 hrs., then 12 hrs. (b) If duty is 8 hrs. or more. then 16 hrs. (c) If staff is required to work train less then stipulated rest then breach of rest allowance is payable to running staff.
10. Separate links should be prepared for superfast trains such as Rajdhani/Shatabdi Exp. Chronic late running trains should be kept in view to avoid link failures.
POINTS TO BE KEPT IN VIEW WHILE PREPARING LOCOMOTIVE LINKS
1. Loco/Power links are prepared by HQ.'s office and circulated to the divisions. The objective of power links is to ensure optimum utilization of powers.
2. Train timings should be checked from latest time table.
3. Links to be prepared before commencement of new time table.
4. Efforts should be made to send the loco to home shed for servicing within the stipulated schedule time
5. Minimum possible out station halt should be provided.
6. Ensure loco is permitted to run on the sections at the max. permissible speed of the train.
POWER REQUIREMENT (POWER PLAN)
1. To be prepared once in six months.
2. Avg. No. of trains run on each section per day and Avg. hours on road for last six months duly signed by Sr.DME(P) and Sr.DOM to be prepared.
3. Formula: Section wise average freight POL for the last six months to be calculated as under: Bare POL = PDD + HOR + PAD (POL=Power on line ; PDD = Pre departure detention; HOR=Hours on road; PAD=Post arrival detention)
4. 3.5 % further growth and 10% Bunching allowance to be demanded on Bare POL
5. Loco's requirement. for DMT. ART. and other loco' s which remain in outage but not added in POL for the purpose of calculation of average kilometers to be added in the bare requirement.
6. To arrive total POL. last six month average POL of shunting loco link WDS-4, WDS-5, WDS-6 pilots and Mail lie over to be added in the POL calculated above.
7. Mail/Exp./Pass. Loco requirement to be worked out on the basis of loco link. Add 10% for major repair allowance.
8. For shunting services, work out number of points for 8 hours shunting, demand 0.33 POL. Add 1 loco as overlap against 06 loco. Add 10% for major repairs.
9. Kms formula: Total kms earned on the Avg. per day during last six months divided by average loco utilization
CREW LINKS, LOCO LINKS AND POWER PLAN
PROCEDURE FOR CALCULATING CREW REQUIREMENT OF A DIVISION
2 a) FORMULA FOR GOODS CREW REVIEW BASED ON CREW HOURS
2 b) TRAINEE RESERVE FOR VARIOUS CATEGORIES OF RUNNING STAFF
3. Review of Loco Pilot (Mail/Express/Passenger):
4. Review of Shunters:
POINTS TO BE KEPT IN VIEW WHILE PRPEARING DRIVER’S LINKS
POINTS TO BE KEPT IN VIEW WHILE PREPARING LOCOMOTIVE LINKS :
POWER REQUIREMENT (POWER PLAN)